Install 5x waste water pump stations
Install cabling and connect 13 street lights

Tags: Lighting / Water Pumps

Outline Of Scope Of Works

Install mains cabling, control cabinets, junction boxes, ultrasonic level sensors and twin pumps to waste water pump stations.

A new site main switchboard with provision for future metering requirements was supplied and installed as per specifications for the main pump station.

After connection, testing and commissioning had been completed we assisted with decommissioning of old pump stations.

Cabling and connection of street lights required the use of an EWP

Project Obstacles to Overcome

The hostile environment of close proximity to the ocean had to be taken into account. Stainless steel and marine grade aluminium were required for all fixings, enclosures and covers.